The Most Expensive Time to Test a Project Budget Is After the Design Is Approved
By Sophia Juodaky MRICS, Senior Associate Quantity Surveyor
-
We are seeing this far too often: a client comes to us with their project budget agreed and the initial design already signed off. The problem? Within weeks of our engagement, our cost estimates show that the budget is not enough.
The example:
On several recent projects, clients have come to us with a project budget agreed internally and signed off before CSQ’s engagement and before any professional feasibility cost review or benchmarking has taken place. As the design developsand our team reviews the project brief, scope, complexity and client requirements, we provide our budget recommendation and realise that thecommercial picture looks very different from what the client had in mind.
The design is not necessarily the problem. In many cases, it follows the client’s brief. The issue is that the budget has never been tested against real marketcosts, current procurement conditions or the actual scope being designed.
A professional cost consultant can also advise on the wider commercial risks that need to be considered. This may include unforeseen costs, specialist services such as acoustic consultants, fees for tenant variations, move management and other client-side requirements. They can also advise on how the client canprotect its commercial position through an appropriate and robust construction contract.
Unfortunately, these scenarios can leave projects in an uncomfortable position, where both cost and time are now at risk from the beginning or from the outset.
Does the client go back to the board for more money? Cut scope they have already committed to? Or delay the project while a decision is made?
These conversations do not need to happen if a cost consultant is involved from the point the project idea is first being considered.


This is a pattern, not a one-off
Examples like this are not isolated cases. It is a pattern we continue to see across the industry.
Cost advice is too often treated as a service to bring in once the wider consultant team is onboard and the budget has already been approved. The thinking isusually well-intentioned: it saves fees early on, allows the project to start quickly and brings in the cost experts once there is something firm to price.
The reality is that a cost consultant can provide valuable advice from the feasibility stage. We see construction costs in real time, have access to extensive internal cost data and can draw on comparable, benchmarked projects.This allows us to establish and justify a realistic budget before it is presented for approval. An internally approved budget is not necessarily aviable project budget. It still needs to be tested against the market, thebrief and the realities of delivery.
What early involvement would have changed
Accurate cost planning.
The budget can be benchmarked against current market rates, prevailing procurement conditions and the cost implications of the client’s brief and specification.
Is the requirement a basic fit-out, or a high-specification designinvolving acoustic glazing, imported materials and branded finishes? Are there additional costs the budget needs to account for? Should the budget include client-direct procurement or specialist consultants? Does the client’s capital expenditure profile require cash flow to be deployed within a defined drawdown period?
Answering these questions before establishing the project budget will help ensure thecost plan is realistic, comprehensive and aligned with the client's objectives, minimising cost surprises later in the project.
Cost planning and design developed concurrently.
As the brief develops, the cost plan should be updated in parallel.
This gives the design team and the client a live commercial picture to inform decisions, rather than relying on a figure with no clear basis. It also means that the cost impact of design decisions can be understood while there is still time to adjust them.
Risk identified and allocated early, not after it materialises.
A cost consultant can flag potential unforeseen costs, set appropriate contingency and risk allowances and advise on contract structure and riskallocation. This helps ensure that the procurement strategy and contract terms reflect the actual risk profile of the project, rather than relying on generic terms that may not be appropriate for construction works.
The result is not just a more accurate budget. It aligns cost, scope and risk from day one, supported by professional, due-diligence-led advice that protects both the commercial position and the programme.
“Where did you get that budget from?”
“What was it based on?”
“How did you arrive at that number?”
By the time the design is approved, these questions should already have clear answers.
Bring your cost consultant in from the outset, at feasibility stage and before thebudget is set. The upfront cost is small compared with the cost of redesign, delay or seeking additional funding later. It sets realistic projectexpectations, reduces programme risk and avoids the conversations no one wantsto have halfway through a project.
CSQ supports clients with feasibility budgeting, cost benchmarking, costplanning, procurement advice and wider cost consultancy services. Engaging early helps establish a realistic commercial foundation before key projectdecisions are made.